Norelli Hargreaves Playground Basketball Courts and Multi-Purpose Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new basketball courts and a multi-purpose play area at Norelli-Hargreaves Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $1,524,000
Funding Source: Borough President

Location

Norelli-Hargreaves Playground, Queens
Van Wyck Expressway, 142nd Street, 106th Avenue
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025