Hallets Cove Playground Multi Purpose Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the multi-purpose play area at Hallets Cove Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Completion Date: June 2021

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $2,607,000
Funding Source: City Council

Location

Hallets Cove Playground, Queens
Vernon Boulevard, Main Avenue, and 8th Street
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024