Devoe Park Perimeter Steel Gates Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install steel gates for the perimeter fence at Devoe Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: September 2017
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $100,000
Funding Source: Mayoral

Location

Devoe Park, Bronx
West Fordham Road, Sedgwick Avenue, Webb Avenue, Father Zeiser Place, University Avenue
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024