Anne Loftus Playground Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the spray shower plaza, children's climber play equipment, and safety surfacing at Anne Loftus Playground in Fort Tryon Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Completion Date: April 2021

Construction

Start Date: August 2021
Projected Completion Date: August 2022
Completion Date: September 2022

Understand how we build parks.

Funding

Total Funding: $3,959,000
Funding Source: City Council

Location

Fort Tryon Park, Manhattan
Broadway and Riverside Drive
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024