Anne Loftus Playground Spray Shower Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the spray shower plaza, children's climber play equipment, and safety surfacing at Anne Loftus Playground in Fort Tryon Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date:
August 2019
Procurement
Start Date: August 2019
Projected Completion Date:
May 2020
Completion
Date:
April 2021
Construction
Start Date: August 2021
Projected Completion Date:
August 2022
Completion Date: September 2022
Understand how we build parks.
Funding
Funding Source: City Council
Location
Fort Tryon Park, Manhattan
Broadway and Riverside Drive
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024