Bellevue South Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an ADA-accessible dog run and reconstruct the basketball court, playground, and sitting areas at Bellevue South Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: September 2020
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $5,049,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Bellevue South Park, Manhattan
1st Avenue, Mount Carmel Place, East 26th Street, East 28th Street
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025