Poor Richard's Playground Play Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play area at Poor Richard's Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
December 2021
Construction
Start Date: February 2022
Projected Completion Date:
February 2023
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Poor Richard's Playground, Manhattan
3rd Avenue between East 108th and East 109th Streets
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project