Inwood Hill Park Ballfields 1, 2 & 4 Reconstruction and Ballfield 1 Lighting Installation

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct ballfields 1, 2 and 4 and install new lighting in ballfield 1 at Inwood Hill Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: October 2022

Procurement

Start Date: October 2022
Projected Completion Date: July 2023
Adjusted Completion Date: December 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Inwood Hill Park, Manhattan
Seaman Avenue and Isham Street
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024