Audubon Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Audubon Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: October 2018
Projected Completion Date: April 2020
Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $5,996,000
Funding Source: Mayoral

Location

Audubon Playground, Manhattan
Audubon Avenue between West 169th Street and West 170th Street
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024