Audubon Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Audubon Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
November 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
August 2018
Completion
Date:
September 2018
Construction
Start Date: October 2018
Projected Completion Date:
April 2020
Completion Date: September 2020