Prescott Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Prescott Playground, including fencing, retaining walls, play equipment, and pavements.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: November 2019

Construction

Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $3,741,000
Funding Source: Borough President

Location

E.M.T. Christopher J. Prescott Playground, Staten Island
Irvington Street and Edith Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project