Naples Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Naples Playground, including the play area, the basketball courts, and the ball field fencing.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2018
Projected Completion Date:
November 2019
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
March 2022
Construction
Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date: May 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Naples Playground, Staten Island
Targee Street, Stanwich Street, Rome Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025