Naples Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Naples Playground, including the play area, the basketball courts, and the ball field fencing.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: May 2023

Understand how we build parks.

Funding

Total Funding: $2,667,000
Funding Source: City Council

Location

Naples Playground, Staten Island
Targee Street, Stanwich Street, Rome Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024