Audubon Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building at Audubon Playground and make it ADA accessible.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
November 2017
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
October 2019
Construction
Start Date: January 2020
Projected Completion Date:
April 2021
Completion Date: May 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Audubon Playground, Manhattan
Audubon Avenue between West 169th Street and West 170th Street
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025