Brooklyn, Queens and Staten Island Reforestation FY18

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new and replacement trees in Brooklyn, Queens, and Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: December 2018

Construction

Start Date: January 2019
Projected Completion Date: June 2021
Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $1,742,000
Funding Source: Mayoral

Location

Various locations in Brooklyn, Queens, and Staten Island.

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025