Melrose Commons Site 62 Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a park at Melrose Commons Site 62, including a synthetic turf field, adult fitness equipment, a dog run, seating areas, drinking fountains, lighting, fences, pavement, plantings, and drainage.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
March 2020
Procurement
Start Date: March 2020
Projected Completion Date:
December 2020
Completion
Date:
January 2022
Construction
Start Date: February 2022
Projected Completion Date:
August 2023
Completion Date: September 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Melrose Commons Park, Bronx
Melrose Avenue between East 162nd Street and East 163rd Street
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025