Melrose Commons Site 62 Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a park at Melrose Commons Site 62, including a synthetic turf field, adult fitness equipment, a dog run, seating areas, drinking fountains, lighting, fences, pavement, plantings, and drainage.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: January 2022

Construction

Start Date: February 2022
Projected Completion Date: August 2023
Completion Date: September 2022

Understand how we build parks.

Funding

Total Funding: $6,081,000
Funding Source: Mayoral

Location

Melrose Commons Park, Bronx
Melrose Avenue between East 162nd Street and East 163rd Street
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025