Pelham Bay Park Sensory Garden Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a barrier-free participatory garden that engages all the senses in enjoying the outdoors in Pelham Bay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019
Completion Date: July 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $497,000
Funding Source: City Council

Location

Pelham Bay Park, Bronx
Bruckner Boulevard and Middletown Road next to Playground For All Children
Community Board: 10, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project