St. James Park Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run in St. James Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021
Completion Date: May 2022

Construction

Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $791,000
Funding Sources:
  • City Council
  • Mayoral

Location

St. James Park, Bronx
Creston Avenue and East 193rd Street
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project