St. James Park Dog Run Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a dog run in St. James Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2018
Projected Completion Date:
February 2019
Completion Date:
August 2020
Procurement
Start Date: August 2020
Projected Completion Date:
May 2021
Completion
Date:
May 2022
Construction
Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
St. James Park, Bronx
Creston Avenue and East 193rd Street
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024