Manhattan Community Garden Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install water service lines at various community gardens in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2018
Projected Completion Date: June 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: November 2020

Construction

Start Date: March 2021
Projected Completion Date: February 2022
Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $591,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Jackie Robinson Community Garden, Manhattan
    103 East 122nd Street
  • Green Oasis and Gilbert's Garden, Manhattan
    East 8th Street between Avenues C & D
  • Maggie's Magic Garden, Manhattan
    Lexington Avenue between East 100th and East 101 Streets
  • Pleasant Village Community Garden, Manhattan
    Pleasant Avenue between East 118 & East 119 Streets
  • William B. Washington Memorial Garden, Manhattan
    West 126th Street between St. Nicholas & Frederick Douglass
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024