Devoe Park Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run at Devoe Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: January 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $764,000
Funding Sources:
  • City Council
  • Mayoral

Location

Devoe Park, Bronx
West Fordham Road, Webb Avenue, Father Zeiser Place, University Avenue
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024