Brooklyn Community Garden Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install water service lines at various community gardens in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2018
Projected Completion Date: June 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: February 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $586,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • Escape To Nature , Brooklyn
    555 Glenmore Avenue
  • United Community Center, Brooklyn
    Corner Of Livonia Avenue and Schenck Avenue
  • P.S. 4 Paradise Garden, Brooklyn
    Glenmore Avenue, Ashford Street, Cleveland Street
  • Green Valley Garden, Brooklyn
    Powell Street and New Lott Avenue
  • Surfside Multi-Cultural Garden Coalition, Brooklyn
    Surf Avenue between West 29 Street and West 28 Street
  • Vernon Cases Community Garden, Brooklyn
    Vernon Avenue between Nostrand & Marcy Avenues
 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025