Playground 174 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play and adult fitness equipment, swings, spray shower, pavements, fencing, lighting, and mini-pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: November 2018

Construction

Start Date: October 2018
Projected Completion Date: January 2020
Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $4,987,000
Funding Source: Mayoral

Location

Captain William Harry Thompson Playground, Bronx
East 174th Street between Bronx River Avenue and Manor Avenue.
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project