Playground 174 Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Public Restroom Building in Playground 174.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
February 2018
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
November 2019
Construction
Start Date: March 2021
Projected Completion Date:
March 2022
Completion Date: April 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Captain William Harry Thompson Playground, Bronx
East 174th Street between Bronx River Avenue and Manor Avenue
Community Board: 09