Mapes Ballfield Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Mapes Ballfield with a new natural turf outfield, recreational sports lighting, play equipment, and adult fitness equipment.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
November 2018
Procurement
Start Date: November 2018
Projected Completion Date:
July 2019
Completion
Date:
July 2019
Construction
Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date: April 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Mapes Park, Bronx
Mapes Avenue and Prospect Avenue between East 180th Street and East 181st Street
Community Board: 06
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025