Broad Channel Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the entry plaza, including new benches, pavement and fencing, at Broad Channel Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
April 2019
Completion Date:
February 2019
Procurement
Start Date: February 2019
Projected Completion Date:
November 2019
Completion
Date:
June 2021
Construction
Start Date: July 2021
Projected Completion Date:
July 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Broad Channel Park, Queens
East 16th Road, Cross Bay Boulevard, Channel Road
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025