Fairview Park Multi-Purpose Field and Landscape Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a multi-purpose field, baseball field, tennis courts, pickleball courts, adult fitness equipment, picnic area, parking area, bio-retention areas, paths, and landscape elements at Fairview Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2015
Projected Completion Date:
June 2017
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
May 2018
Completion
Date:
December 2018
Construction
Start Date: February 2019
Projected Completion Date:
August 2020
Completion Date: May 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
- Mayoral
Location
Fairview Park, Staten Island
Arthur Kill Road and Veterans Road West
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project