Bronx, Manhattan and Queens Park Trees Planting and Replacement
-
100% complete
-
100% complete
-
100% complete
This project will plant new park trees in the Bronx, Manhattan and Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
December 2017
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
May 2019
Completion
Date:
September 2019
Construction
Start Date: October 2019
Projected Completion Date:
April 2021
Completion Date: April 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations in the Bronx, Manhattan and Queens
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024