Parkside Playground Green Infrastructure Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture stormwater at Parkside Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2017
Projected Completion Date:
December 2018
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Completion
Date:
November 2022
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Completion Date: July 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Parkside Playground, Bronx
Arnow Avenue, Olinville Avenue.
Community Board: 11
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025