Fairview Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new public restroom building at Fairview Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2015
Projected Completion Date:
December 2017
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
July 2019
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
- Mayoral
Location
Fairview Park, Staten Island
Bricktown Way between Arthur Kill Road & Veterans Road West
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project