Bronx Park Adult Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an adult fitness area in Bronx Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: March 2020
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $276,000
Funding Sources:
  • City Council
  • Mayoral

Location

Bronx Park, Bronx
Bronx Park East between Arnow Avenue and Britton Street
Community Board: 06, 07, 11, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024