Staten Island Street Tree Planting FY18
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
August 2017
Completion Date:
September 2017
Procurement
Start Date: September 2017
Projected Completion Date:
June 2018
Completion
Date:
February 2019
Construction
Start Date: March 2019
Projected Completion Date:
August 2020
Completion Date: March 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 11/22/2024