Queens PlaNYC Street Tree Planting FY18 - Community Boards 7,8,11

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 7, 8, and 11 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: August 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $2,990,000
Funding Source: Mayoral

Location

Various locations in Queens