Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
August 2017
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
September 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2020
Completion Date: September 2020