Brooklyn Street Tree Planting FY18 - Community Boards 6,7,10,12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Brooklyn Community Boards 6, 7, 10, and 12.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: August 2017
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: February 2020
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $2,999,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024