Brooklyn Street Tree Planting FY18 - Community Boards 5,14,18
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 5, 14, and 18 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
August 2017
Completion Date:
September 2017
Procurement
Start Date: September 2017
Projected Completion Date:
June 2018
Completion
Date:
June 2018
Construction
Start Date: August 2018
Projected Completion Date:
February 2020
Completion Date: December 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024