Bronx Street Tree Planting FY18 - Community Boards 1-8
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 1-8 in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
August 2017
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
September 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date: January 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 01/17/2025