Highbridge Anchor Park Reconstruction Phase II
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Adventure Playground and Sunken Playground, install park pathway lighting to the historic High Bridge, and construct a new synthetic turf practice field at Highbridge Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2017
Projected Completion Date:
May 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
June 2019
Construction
Start Date: July 2019
Projected Completion Date:
January 2021
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highbridge Park, Manhattan
Along Edgecombe Avenue between West 163rd and West 166th Streets
Community Board: 10, 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024