Highbridge Anchor Park Reconstruction Phase II

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Adventure Playground and Sunken Playground, install park pathway lighting to the historic High Bridge, and construct a new synthetic turf practice field at Highbridge Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: January 2021
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $11,830,000
Funding Source: Mayoral

Location

Highbridge Park, Manhattan
Along Edgecombe Avenue between West 163rd and West 166th Streets
Community Board: 10, 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024