Flushing Meadows Corona Park Lawrence Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Public Restroom Building at Lawrence Playground in Flushing Meadows Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
May 2017
Completion Date:
April 2018
Procurement
Start Date: April 2018
Projected Completion Date:
December 2018
Completion
Date:
April 2019
Construction
Start Date: September 2019
Projected Completion Date:
March 2021
Completion Date: May 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
Van Wyck Expressway, Botanical Garden Bridge, College Point Boulevard
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024