Betsy Head Park Public Restroom Building & Utility Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Public Restroom Building and utility building in Betsy Head Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
March 2020
Construction
Start Date: October 2020
Projected Completion Date:
March 2022
Completion Date: December 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Betsy Head Park, Brooklyn
Corner of Strauss Street and Livonia Avenue
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025