Betsy Head Park Synthetic Turf Field, Track, Sport Courts and Adult Fitness Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a synthetic turf field, rubberized track, sport courts and adult fitness equipment area at Betsy Head Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Construction

Start Date: September 2019
Projected Completion Date: February 2021
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $13,596,000
Funding Source: Mayoral

Location

Betsy Head Park, Brooklyn
Livonia Avenue, Strauss Street and Dumont Avenue
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025