Hook Creek Park Sediment Application

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will apply a thin layer of sediment within the wetland area of Hook Creek Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2020
Projected Completion Date: September 2021
Completion Date: July 2021

Procurement

Start Date: July 2021
Projected Completion Date: April 2022
Completion Date: September 2022

Construction

Start Date: October 2022
Projected Completion Date: June 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Hook Creek Park, Queens
In the wetland area near Huxley Street and Craft Avenue.
Community Board: 13

 

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025