Alley Pond Park Living Shoreline Construction Phase 2

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a living shoreline along the western shore of Alley Creek at Alley Pond Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: May 2022

Procurement

Start Date: March 2021
Projected Completion Date: December 2021
Completion Date: December 2022

Construction

Start Date: January 2023
Projected Completion Date: July 2023
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Cross Island Parkway, Queens
Western shoreline of Alley Creek near Cross Island Parkway and Northern Boulevard
Community Board: 07, 11, 13

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024