Alley Pond Park Living Shoreline Construction Phase 2
-
100% complete
-
100% complete
-
100% complete
This project will construct a living shoreline along the western shore of Alley Creek at Alley Pond Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
May 2022
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Completion
Date:
December 2022
Construction
Start Date: January 2023
Projected Completion Date:
July 2023
Completion Date: June 2023
Understand how we build parks.
Funding
Location
Cross Island Parkway, Queens
Western shoreline of Alley Creek near Cross Island Parkway and Northern Boulevard
Community Board: 07, 11, 13
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025