Citywide HVAC Controls Building Automation Systems Installation
-
100% complete
-
60% complete
-
0% complete
This project will install automated HVAC system controls at various parks facilities citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2021
Projected Completion Date:
April 2021
Completion Date:
October 2023
Procurement
Start Date: October 2023
Projected Completion Date:
October 2024
Adjusted Completion
Date:
May 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Chelsea Recreation Center, Manhattan
Southside West 25 Street, 9 to 10 Avenues
Community Board: 04 -
Constance Baker Motley Recreation Center, Manhattan
East 54th Street between 1st and 2nd Avenues.
Community Board: 06 -
Jackie Robinson Park, Manhattan
85 Bradhurst Avenue
Community Board: 09, 10 -
Julio Carballo Fields, Bronx
Manida Street, Barretto Street, Lafayette Avenue
Community Board: 02 -
Randall's Island Park, Manhattan
East & Harlem Rivers
Community Board: 11 -
Red Hook Recreation Area, Brooklyn
Otsego, Bay, Hicks, Lorraine, Court, Halleck Streets
Community Board: 06 -
Roy Wilkins Recreation Center, Queens
Baisley & Merrick Boulevards, 115 Avenue
Community Board: 12 -
St. John's Park, Brooklyn
Troy Avenue, Bergen Street, Prospect Place, Schenectady Avenue
Community Board: 08
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024