Citywide HVAC Controls Building Automation Systems Installation

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will install automated HVAC system controls at various parks facilities citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: April 2021
Completion Date: October 2023

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Adjusted Completion Date: May 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024