Owl Hollow Fields Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    20% complete

This project will construct a public restroom building at Owl Hollow Fields in Freshkills Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: November 2019
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: January 2022
Completion Date: November 2023

Construction

Start Date: December 2023
Projected Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $4,246,000
Funding Source: Mayoral

Location

Freshkills Park, Staten Island
Arthur Kill Road near Arden Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024