Owl Hollow Fields Public Restroom Building Construction
-
100% complete
-
100% complete
-
38% complete
This project will construct a public restroom building at Owl Hollow Fields in Freshkills Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2018
Projected Completion Date:
November 2019
Completion Date:
March 2023
Procurement
Start Date: March 2023
Projected Completion Date:
January 2022
Completion
Date:
November 2023
Construction
Start Date: December 2023
Projected Completion Date:
June 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Freshkills Park, Staten Island
Arthur Kill Road near Arden Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025