Owl Hollow Fields Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    38% complete

This project will construct a public restroom building at Owl Hollow Fields in Freshkills Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: November 2019
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: January 2022
Completion Date: November 2023

Construction

Start Date: December 2023
Projected Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $4,314,000
Funding Source: Mayoral

Location

Freshkills Park, Staten Island
Arthur Kill Road near Arden Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025