Mariners Harbor Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Mariners Harbor Playground with new play equipment, pavements, curbs, fences, walls and planting.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: April 2020

Construction

Start Date: September 2020
Projected Completion Date: March 2022
Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $3,090,000
Funding Sources:
  • City Council
  • Mayoral

Location

Bobbie Lewis Jr. Playground , Staten Island
Harbor Road between Richmond Terrace and Leyden Avenue
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project