Mariners Harbor Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Mariners Harbor Playground with new play equipment, pavements, curbs, fences, walls and planting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
April 2020
Construction
Start Date: September 2020
Projected Completion Date:
March 2022
Completion Date: November 2021
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Bobbie Lewis Jr. Playground , Staten Island
Harbor Road between Richmond Terrace and Leyden Avenue
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024