Playground One Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Playground One.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: April 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $2,508,000
Funding Source: Mayoral

Location

Playground One, Manhattan
Madison Street between Oliver Street and Catherine Street
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024