Playground One Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Playground One.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
April 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Playground One, Manhattan
Madison Street between Oliver Street and Catherine Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024