Joseph Sauer Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Joseph Sauer Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
July 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date: December 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Joseph C. Sauer Park, Manhattan
East 12th Street between Avenue A & Avenue B
Community Board: 03
Project Staff
Project Liaison: Steve Simon