Prospect Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Prospect Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $6,358,000
Funding Source: Mayoral

Location

Prospect Playground, Bronx
East 176th Street between Clinton Avenue and Prospect Avenue
Community Board: 06

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024