Betsy Head Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a public restroom building at Imagination Playground in Betsy Head Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: October 2019

Construction

Start Date: December 2019
Projected Completion Date: June 2021
Completion Date: May 2023

Understand how we build parks.

Funding

Total Funding: $4,001,000
Funding Sources:
  • City Council
  • Mayoral

Location

Betsy Head Park, Brooklyn
Bristol Street between Blake Avenue and Dumont Avenue
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024