Brooklyn Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    52% complete

This project will construct green infrastructure to capture storm water at Classon Playground, Colonel David Marcus Playground and Oracle Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: December 2018
Completion Date: April 2021

Procurement

Start Date: April 2021
Projected Completion Date: January 2022
Completion Date: April 2023

Construction

Start Date: February 2024
Projected Completion Date: February 2025