Brooklyn Green Infrastructure Construction
-
100% complete
-
100% complete
-
52% complete
This project will construct green infrastructure to capture storm water at Classon Playground, Colonel David Marcus Playground and Oracle Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
December 2018
Completion Date:
April 2021
Procurement
Start Date: April 2021
Projected Completion Date:
January 2022
Completion
Date:
April 2023
Construction
Start Date: February 2024
Projected Completion Date:
February 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Classon Playground, Brooklyn
Lafayette & Classon Avenues
Community Board: 02 -
Colonel David Marcus Playground, Brooklyn
Ocean Parkway, Avenue P, East 3 Street
Community Board: 12 -
Oracle Playground, Brooklyn
Adelphi & Myrtle Avenues
Community Board: 02
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024