Queens Green Infrastructure Construction (QG-518M)
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture storm water at Helen Marshall Playground, Electric Playground, Horace Harding Playground, London Planetree Playground, and Joseph P. Addabbo Memorial Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2018
Projected Completion Date:
June 2019
Completion Date:
February 2021
Procurement
Start Date: February 2021
Projected Completion Date:
November 2021
Completion
Date:
April 2023
Construction
Start Date: June 2023
Projected Completion Date:
December 2024
Completion Date: September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Electric Playground, Queens
W/S 164 Street, S/O 65 Avenue
Community Board: 08 -
Helen Marshall Playground, Queens
25th Avenue & 98th Street.
Community Board: 03 -
Horace Harding Playground, Queens
62 Drive between 97 Place & 98 Street
Community Board: 06 -
London Planetree Playground, Queens
88th Street, Atlantic Avenues, 95 Avenue
Community Board: 09 -
Tudor Park, Queens
North Conduit Avenue, between 80 and 88 Streets, 133 Avenue
Community Board: 10