Queens Green Infrastructure Construction (QG-518M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct green infrastructure to capture storm water at Helen Marshall Playground, Electric Playground, Horace Harding Playground, London Planetree Playground, and Joseph P. Addabbo Memorial Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2018
Projected Completion Date: June 2019
Completion Date: February 2021

Procurement

Start Date: February 2021
Projected Completion Date: November 2021
Completion Date: April 2023

Construction

Start Date: June 2023
Projected Completion Date: December 2024
Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $4,844,000
Funding Source: Mayoral

Locations

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024