Bloomingdale Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Bloomingdale Playground, bringing it into compliance with ADA accessibility standards.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
April 2017
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
January 2018
Completion
Date:
May 2018
Construction
Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date: September 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bloomingdale Playground, Manhattan
Amsterdam Avenue between West 104th Street and West 105th Street
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025