Highbridge Bathhouse Boiler Reconstruction and Air Conditioning Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    83% complete

This project will reconstruct boilers and related plumbing and provide a new heating, ventilating, and air conditioning system for Highbridge Bathhouse.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2016
Projected Completion Date: March 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: August 2019
Completion Date: April 2021

Construction

Start Date: September 2021
Projected Completion Date: September 2022
Adjusted Completion Date: December 2024

Understand how we build parks.

Funding

Total Funding: $5,015,000
Funding Sources:
  • City Council
  • Mayoral

Location

Highbridge Park, Manhattan
2301 Amsterdam Avenue
Community Board: 10, 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024