Battery Park Coast Guard Monument Relocation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will relocate the Coast Guard Monument in Battery Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2016
Projected Completion Date: May 2017
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: August 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $601,000
Funding Source: Private

Location

The Battery, Manhattan
State Street and South Street
Community Board: 01

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024