Battery Park Coast Guard Monument Relocation
-
100% complete
-
100% complete
-
100% complete
This project will relocate the Coast Guard Monument in Battery Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2016
Projected Completion Date:
May 2017
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
August 2019
Completion
Date:
November 2019
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: September 2021
Understand how we build parks.
Funding
Funding Source: Private
Location
The Battery, Manhattan
State Street and South Street
Community Board: 01
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024